Implementation Plan
for Management of a Global Environment Facility Project Development Fund Block B Grant
for the project
“Building the Inter-American Biodiversity Information Network (IABIN)”

(Short title:  IABIN PDF Project Plan)

D*R*A*F*T — 7 Jan 2002

 

Countries: Hemisphere Wide
Requesting Agency:  World Bank
Executing Agency (PDF): Organization of American States (OAS)
Country Implementing:  IABIN Focal Points as indicated by Governments
PDF Block B Funds Requested: US$650,000

A.  ACTIVITIES

As outlined in the proposal to the Global Environment Facility (GEF) for a Project Development Fund (PDF) Block B Grant, the following specific activities will be undertaken during the project preparation phase:

1.   Define requirements for network content and architecture

a.       Develop and apply a survey instrument to document network and content requirements of IABIN participants.

b.       Identify potential IABIN participants, both individual and organizational, as well as other appropriate experts to participate in defining requirements for the network.

c.       Develop studies and background documentation on issues, projects, and other topics relevant to better design of the GEF project (intellectual property rights, new infrastructure technologies, telecommunications capacity in the region, directories of experts or networks of biodiversity information in the region, etc.).

d.       Convene three regional meetings of biodiversity experts to determine network and content requirements for IABIN and document any special sub-regional activities that would support IABIN development. The regional meetings will be held in Central America, the Caribbean, and South America. An additional output of the regional meetings and IABIN activities in general will be to prepare a Latin American and Caribbean position on environmental information for the World Summit in Johannesburg and contribute to the GEF/Clearing-House Mechanism (CHM) position.

e.       Assess the availability of the various types of biological information identified as relevant content for IABIN and set priorities for the incorporation of that content.

f.        Prepare a report with the findings from the requirements definition process.

2.   Institute collaborative partnerships with other initiatives and organizations

a.       Conclude a formal Memorandum of Cooperation with the Secretariat of the Convention on Biological Diversity (CBD) defining the collaboration between IABIN and the CHM and describing the role and the value added by IABIN to the implementation of the CHM.

b.       Identify successful national and subregional initiatives, such as REMIB, which can be considered prototypes for IABIN, and define how a hemisphere-wide network can build on these initiatives.

c.       Establish collaborations, including formal agreements where necessary, with other relevant initiatives including, inter alia, the GBIF, the Biodiversity Conservation Information System (BCIS), NABIN, and thematic initiatives such as the Global Invasive Species Programme.

d.       Develop explicit working relationships, including agreements for information-sharing, with international and national academic institutions, private enterprise, and NGOs (e.g., World Resources Institute, Conservation International, The Nature Conservancy, Association for Biodiversity Information, the Smithsonian, etc.).

e.       Build on the study currently underway on a financial sustainability strategy for IABIN.

3.   Develop an infrastructure implementation plan

a.       Define the technical details of the network architecture, including the sources of biodiversity information content, catalogues, standards and protocols for information sharing.

b.       Develop a multi-year infrastructure implementation plan; include estimates of the resources required for each stage of implementation.

c.       Assess capacity gaps, particularly within developing countries, to facilitate access to the IABIN infrastructure and its information sources.

d.       Indicate priority areas for infrastructure development.

e.       Define the details of implementing a financial sustainable base for infrastructure implementation and maintenance.

4.   Support communication and coordination among participants

a.       During the planning phase, continue development and maintenance of an international IABIN Web site and email communication groups.

b.       Coordinate participants in IABIN projects (e.g., the IABIN Invasives Information Network project) and working groups addressing the activities of the PDF process.

c.       Keep all participating organizations informed of progress.

5.   Develop GEF Project Appraisal Document (PAD)

The PAD will reflect the results of the requirements definition and will lay out a multi-year implementation of the IABIN network.

a.       Prepare a draft PAD by integrating the user needs assessment, network requirements findings, network implementation plan, and resource and capacity-building requirements.

b.       Coordinate a review of the PAD by scientists, policy-makers, and information specialists in the biodiversity community, as well as by staff of the CHM.

c.       Convene a meeting of the IABIN Council for a final review of the PAD.

d.       Publish an informational brochure for potential IABIN participants summarizing the findings and describing the proposed GEF project.

6.   Administration

a.       Provide project management and coordination, meeting logistics support, and overall support to communication among participants.  Administration costs are to be co-financed with the OAS.

b.       Begin implementation of the strategy to establish a sustainable financial base for IABIN.

 

B.     OUTPUTS

1.       Documentation of the user requirements for a network on biodiversity information and an assessment of available content.

2.       Identification of network components (content, standards, tools, etc.) needed to implement IABIN

3.       A multi-year plan for the implementation of IABIN

4.       A redesigned, functioning Web portal with access to operational (if not yet fully developed) tools such as data catalogues and search tools

5.       Memoranda of Cooperation or Understanding between IABIN and other initiatives (e.g., CHM, GBIF, BCIS, Global Invasive Species Program)

6.       A GEF Project Appraisal Document (PAD)

 

C.     PROJECT MONITORING AND EVALUATION

IABIN implementation to date has progressed in two areas: (i) the initiation of specific projects to address biodiversity issues (e.g., invasive species), network standards (e.g., metadata), and tools (e.g., a distributed database search engine); and (ii) the development of a consultative process to encourage the participation of individuals and institutions from public and private sectors in the countries of the Americas.  To track these and new developments, a monitoring and evaluation (M&E) plan will be designed and implemented to ensure monitoring and evaluation of project preparation results.  The M&E plan would be used on a continuing basis during project preparation and amended as needed during project implementation.  The plan will also serve as a basis for disseminating project results to participating states and other countries/regions.

 

D.     MILESTONES

1.       Identification of the technical requirements for a network architecture.

2.       Identification biodiversity information resources available from IABIN participants and their constituencies.

3.       Completion of an inventory of the information needs of the biodiversity community in the region, with indications of priorities among those needs.  The inventory should include identification of gaps in knowledge.

4.       Establishment of a timeframe for participant concurrence  on a set of standards, protocols, tools, and methodologies that will enhance the ability to integrate information across the network.

5.       Development of a strategy for communicating with and engaging data providers in the implementation of the network.

6.       Completion of an inventory of the state of collections of Latin American specimens in North America and Europe and identification of non-electronic data of interest.

7.       Commencement of the implementation of the financial sustainability strategy recommended for IABIN.

 

E.      PERFORMANCE INDICATORS

1.       Quality of project management and coordination, meeting logistics support, and overall support to communication among participants.

2.       Quality of project preparation documents that would be disseminated to other countries, regions and institutions. Replication of Hemispheric networks elsewhere would be supported by production of written material as well as participation in international workshops and task forces.

3.       Quality of interactions of IABIN with CHM Program and the CBD Secretariat, and mention in Conference of Parties decisions.

4.       Identification of national and subregional initiatives, such as REMIB, that can be considered prototypes for IABIN, and definition of how a hemisphere-wide network can build on these initiatives.

5.       Establishment of successful collaborations, including formal agreements where necessary, with other relevant initiatives including, inter alia, the GBIF, the Biodiversity Conservation Information System (BCIS), NABIN, and thematic initiatives such as the Global Invasive Species Programme.

6.       Successful establishment of working relationships, including agreements for information-sharing, with international and national academic institutions, private enterprise, and NGOs (e.g., World Resources Institute, Conservation International, The Nature Conservancy, NatureServe, the Smithsonian).

7.       Increased awareness by decision makers and civil society regarding the value and importance of IABIN.

8.       Success of the IABIN web portal in keeping the general public, as well as project participants, informed in a complete and timely manner concerning the progress of the implementation of IABIN. 

 

F.      INSTITUTIONAL ARRANGEMENTS

Executing Agency:  Given the multi-country nature of the project, the OAS Charter to convene hemispheric meetings, and the infeasibility of splitting project funds into individual country sub-budgets, the OAS/USDE (Unit for Sustainable Development and Environment) will serve as the Executing Agency for the Block B grant on behalf of the participant countries. The OAS will be responsible to the IABIN Executive Committee (IEC), the World Bank (as Implementing Agency) and GEF, and will ensure that applicable rules and procedures are adhered to.   The General Secretariat of the OAS, as the designated recipient of the Grant funds in representation of the beneficiary countries, will be the executing entity for the Project and thus responsible for compliance with Bank procurement procedures.   In addition, the OAS will fulfill an integrating functions for this PDF project and provide general administrative oversight.  The OAS will provide support, as needed, in the procurement, legal, and financial management areas to facilitate Project preparation and will provide a project assistant.

 

Direction and Review:  All the proposed activities will be directed and reviewed by the IABIN Executive Committee (IEC).  The IEC is presently composed of  the following representatives:

·         United States:  US Geological Survey (Chair)

·         Jamaica:  Institute of Jamaica  (Vice-Chair)

·         Argentina:  Ministerio de Relaciones Exteriores, Comercio Internacional y Culto

·         Brazil:  Ministerio do Meio Ambiente, Recursos Hidricos e Amazonia (MMA)

·         Colombia:  Instituto Alexander von Humboldt

·         Dominican Republic:  Secretaria de Medio Ambiente y Recursos Naturales

·         Guatemala:  Comisión Nacional del Medio Ambiente de Guatemala (CONAMA)

·         Mexico:  Comisión Nacional para el Conocimiento y Uso de la Biodiversidad (CONABIO)

·         IGO/NGO Representative:  North American Biodiversity Information Network (NABIN)

 

The IEC will meet as necessary over the course of the project to ensure its successful completion.   These meetings may be by video-conference (using facilities kindly offered by the World Bank), teleconference, electronic or in person. 

In all cases, the IEC will strive for consensus in their direction to the Executing Agency.  However, if no consensus can be reached among the IEC members concerning an issue presented to it, a two-thirds agreement of the members shall be sufficient to render a decision.  Except in extraordinary circumstances, the IEC shall be expected to respond within 10 days from receipt of a request for a decision.  Silence shall be understood to indicate consent.

 

National Coordination:  OAS will work closely with the National IABIN Focal Points to execute the Project under the direction and leadership of the IEC.  The National IABIN Focal Points may further establish in-country technical advisory groups or other such structure in order to inform a country’s input to this process; however, all communications between Project Management and participating countries will be with the National IABIN Focal Points.  It is expected that in-country participant groups will include representatives from government (federal, state, provincial, etc.), NGOs, universities, and other sectors of civil society, as determined by each country.

 

G.     CAPABILITIES OF THE EXECUTING AGENCY 

Procurement issues.  On a recently approved full GEF project, a procurement capacity assessment of OAS was carried out in October 2001 by a World Bank Procurement Specialist, with satisfactory findings, and approved by the Regional Procurement Advisor.  (The full assessment is included in the Guarani Aquifer Project files.)

Financial management issues.  Also for the Guarani Aquifer Project, a financial management assessment was carried out by a World Bank Financial Management Officer, with the OAS receiving a satisfactory rating.

Procurement and disbursement issues.  As stated above, a capacity assessment was carried out by the World Bank at OAS headquarters in Washington, D.C.  It was deemed that the OAS has the necessary infrastructure and human resources, both in headquarters and in the resident missions in most of the beneficiary countries, to carry out and manage its procurement in an orderly and well established manner.  OAS has experience in executing projects financed by various other external sources, some of which call for particular procurement requirements; such is the specific case of an on-going GEF Project in the Caribbean (Adaptation to Global Climate Change).

 

H.     PROJECT MANAGEMENT

Project Team:  A Preparation Unit will be housed within the OAS to prepare the Project. PDF funds budgeted for administration (maximum 10% of total) will be used to help cover costs of this unit (project assistant, consultants, operational and administrative costs). Part of the costs, notably those related to the use of in-house expertise, space and equipment, will be covered by the OAS.

Interaction with IEC:  OAS will provide the IEC with quarterly progress and financial reports.  Reports shall include, at a minimum:  work underway; accomplishments to date; funds committed, obligated, expended and remaining; problems encountered and status of resolution; and issues on which the OAS seeks the guidance or approval of the IEC.

Consultancies:  Specialized consultancies and studies for detailed project and component design, including preparation of the PAD, will be contracted. These studies would specifically include, inter alia:

¾     Requirements definition (e.g., needs analysis)

¾     Network design (both architecture and content)

¾     Incremental cost analysis

¾     Project budgets and schedules

¾     Background and issue papers (topics to be determined), including recommendations

Procurement Planning:  Finance and procurement actions will be handled by OAS financial administrators and procurement specialists.   Two documents will be produced during the PDF project:

1.       A Global Procurement Action Plan for the 12 months of the PDF project will be developed within 3 months of grant award and presented to the IEC for endorsement.  This Procurement Plan will update and add specificity to the PDF budget as outlined in the GEF Proposal (see annex 1).  The Plan will include:

a.       Terms of Reference (TORs) and estimated costs for each consultant activity foreseen in the project preparation period

b.       Description of the procedures for planning, awarding and reporting on consultant activities

c.       Document flow, thresholds, methods and steps to be followed for each anticipated type of procurement

d.       Thresholds over which prior review by the World Bank is required

e.       Monitoring Plan that lists planned actions, outcomes, timeframe, expected impacts, institutions and stakeholders involved, responsible institution(s), and performance evaluation criteria.

For each proposed task, the Global Procurement Action Plan will include the following information:  Component, responsible entity, activity, person months required, value of the contract, financing percentages by agency, terms of reference, approval by the World Bank (if necessary), procurement method (e.g., quality-based), proposal evaluation, date contract awarded, date signed by the vendor, and any observations.

2.       A draft Operations Manual, acceptable to the World Bank, that outlines the organization and responsibilities of the team executing the full-size project and the applicable procedures and requirements the team will follow.  The manual will be prepared within 6 months of the grant award.  Annexes to the Manual would include internal forms and standard Bank documents.   The draft Manual will be finalized by the end of the PDF project and will be included as supporting documentation to the PAD to be submitted to the GEF.

Consultant Services:  The Block B grant will finance, inter alia, specialized studies.  All contracts will be done in compliance with approved procedures and rules of the OAS, and budgetary and financial rules of the OAS and the World Bank.  Recruitment would be done according to Section V of the Bank Consultants Guidelines.

Training Services:  The Project includes organization of workshops and seminars. This category would cover rents, training materials, food, travel expenses, facilitator fees, etc. To the extent applicable, training services would be awarded through price comparison.

Goods:  No goods purchases are foreseen in implementation of the Block B Grant.

Tranche Disbursements:  Funds will be provided to the Executing Agency in two (2) tranches each equal to 40% of the total award and a final tranche equal to 20% of the total award.

 

I.       SCHEDULE

It is presently anticipated that Project preparation will be substantially completed by 12 months after the Block B grant is awarded.   (ECD = Estimated Completion Date)

Activity

Task

Lead

Budget

ECD

1. Define requirements for network architecture and content

 

 

 

 

a.  Develop and apply survey instrument to document network requirements

Develop TOR; hire consultant

 

20,000

 

 

Develop survey

 

 

 

 

Apply survey; document results

 

 

 

b.  Identify potential IABIN participants for requirements definition

Inventory participants

 

 

 

 

Convene technical working group meeting; document results

 

15,000

 

c.  Prepare special studies, projects and background documentation

TBD

 

100,000

 

d.  Convene three regional meetings of biodiversity experts

Recruit hosts

 

 

 

 

Develop TORs for meeting support

 

 

 

 

Hire mtg support consultants

 

 

 

 

Convene CA regional

 

25,000

 

 

Convene Carib regional

 

25,000

 

 

Convene SA regional

 

25,000

 

e.  Prepare report

Write summary requirements definition

 

10,000

 

 

Present to IABIN Council

 

 

 

2. Institute collaborative partnerships

 

 

25,000

 

a.  Conclude MOC with CBD Secretariat

Conclude MOU

 

 

 

b.  Identify initiatives and define how to build on them

(Working Group?  Regionals? Consultant?)

 

 

 

c.  Establish collaboration with GBIF, BCIS, NABIN, GISP, etc.

(MOUs? Exchange of representatives?)

 

 

 

d.  Develop agreements for information-sharing with international and national academic institutions, private enterprise, and NGOs

TBD

 

 

 

e.  Implement financial sustainability strategy

TBD

 

 

 

3. Develop infrastructure implementation plan

 

 

175,000

 

a.  Define technical details of architecture, including content, standards, protocols, catalogues, etc.

Develop TOR; hire consultant

 

 

 

b.  Develop implementation plan with resource estimates

Same consultant as above

 

 

 

c.  Assess infrastructure capacity gaps

Same consultant as above

 

 

 

d.  Define priority areas for infrastructure development

Convene technical working group

 

 

 

e.  Define details of financial sustainable base for implementation and maintenance

Convene technical working group

 

 

 

4. Support communication and coordination among participants

 

 

50,000

 

a.  Develop and maintain international web site and listserv(s)

Select web site host

 

 

 

 

Regain domain name

 

 

 

 

Wrote TOR; hire webmaster

 

 

 

 

Re-implement web site

 

 

 

b.  Coordinate among IABIN project participants, working groups, etc.

Recruit listserv hosts

 

 

 

 

Initiate listservs

 

 

 

c.  Keep participating organizations informed of progress

(Listserv?  Newsletters?)

 

 

 

5. Develop GEF Project Document

 

 

 

 

a.  Prepare draft PAD

Write TOR; hire consultant

 

50,000

 

 

Gather information from consultative processes

 

 

 

 

Draft PAD

 

 

 

b.  Coordinate review of PAD

Circulate PAD for comment

 

5,000

 

 

Incorporate comments

 

 

 

c.  Convene IABIN Council Meeting

Convene meeting

 

50,000

 

d.  Publish information brochure

Write TOR; hire consultant

 

10,000

 

 

Design brochure based on PAD

 

 

 

 

Circulate brochure for review

 

 

 

 

Publish brochure

 

 

 

6. Administration

 

 

 

 

a.  Provide project management coordination; meeting logistics support; etc.

 

 

65,000

 

 

b.  Begin implementation of financial sustainability strategy

 

 

 

 

TOTAL

 

 

650,000

 

 

ANNEX 1

PDF Block B Budget
(as included in proposal)

PDF Activity

Timeframe

GEF

Other

OAS & WB

1. Define requirements for network architecture and content

 

 

 

 

Develop and apply survey instrument to document network requirements

Jan – Dec 02

20,000

10,000

 

Convene Technical Working Group meeting

February-02

15,000

62,000

 

Prepare special studies, projects and background documentation

Jan – Jun 02

100,000

2,500,000

250,000

Convene three regional meetings of biodiversity experts

Mar – May 02

75,000

102,000

30,000

Prepare report

June-02

10,000

20,000

 

2. Institute collaborative partnerships

 

25,000

300,000

40,000

Expand partnership with the CHM

Jan – Oct 02

 

 

 

Develop collaborative efforts

Jan – Oct 02

 

 

 

Develop agreements for information-sharing with international and national academic institutions, private enterprise, and NGOs

Jan – Oct 02

 

 

 

Implement financial sustainability strategy

Jan – Oct 02

 

 

 

3. Develop infrastructure implementation plan

 

175,000

26,000

30,000

Design infrastructure; develop implementation plan

Jul – Sep 02

 

 

 

Submit draft to IABIN Executive Committee, IABIN Council

October-02

 

 

 

4. Support communication and coordination among participants

 

50,000

20,000

 

Maintain Web site and listserv

Jan – Dec 02

 

 

 

Coordinate among IABIN project participants and PDF working groups

Jan – Dec 02

 

 

 

Keep participating organizations informed of progress

Jan – Dec 02

 

 

 

5. Develop GEF Project Document

 

 

 

 

Prepare draft GEF Project Document

October-02

50,000

20,000

 

Coordinate review of GEF Project Document

November-02

5,000

46,000

 

Convene IABIN Council Meeting

December-02

50,000

104,000

 

Publish information brochure

December-02

10,000

20,000

 

6. Administration

 

 

 

 

Provide project management coordination; meeting logistics support; etc.

Jan - Dec 02

65,000

220,000

90,000

 

 

 

 

 

TOTAL

 

650,000

3,450,000

440,000

 

 

 

 

 

PDF REQUEST TOTALS

 

650,000

 

 

Total project support funds and in-kind contributions

 

 

3,890,000

 

 

Back to Top of Page
 
This site is maintained and hosted by the National Biological Information Infrastructure  NBII
Text only
Credits
Disclaimer
http://www.iabin-us.org
Last Updated:
International IABIN Site